Proper invoices, the Prompt Payment Act clock, WAWF and IPP, cost-type vouchers, and how long you have to bill after the work is done.
Last reviewed on September 28, 2026 by the Government.biz editorial team against FAR Subpart 32.9, FAR 52.216-7 and 52.232-7 (FAC 2026-01), and Treasury's Prompt Payment guidance.
The government pays against proper invoices submitted electronically to the billing office named in your contract, after the work or delivery has been accepted. For most fixed-price work the Prompt Payment Act sets a 30-day clock and requires the agency to pay interest automatically if it pays late. Cost-reimbursement and time-and-materials contracts are paid through vouchers, which follow their own clauses and end with a completion voucher after the work — and, for cost-type contracts, indirect rates — are settled. Almost every payment problem a small business runs into traces to one of three things: an invoice that is not "proper," a missing acceptance, or a registration and routing mismatch.
The Prompt Payment Act (31 U.S.C. Chapter 39), implemented at FAR Subpart 32.9, 5 CFR Part 1315, and the clause at FAR 52.232-25 (or the payment terms in FAR 52.212-4 for commercial contracts), controls when the government must pay.
If the agency pays after the due date and you submitted a proper invoice, acceptance occurred, and there is no dispute over quantity, quality, or compliance, the payment office must add an interest penalty automatically — you do not have to ask (FAR 32.907). Interest is computed under 5 CFR Part 1315 using the rate the Treasury publishes every six months; for July 1 through December 31, 2026 the Prompt Payment interest rate is 4.75%. Interest compounds in 30-day increments.
If the payment office pays the principal but not the interest owed (and the interest is at least $1), you can demand an additional penalty — but only by a written demand to the payment office postmarked within 40 days after the invoice amount was paid. Interest is not owed on amounts in dispute or on amounts properly withheld under the contract; those are resolved under the Disputes clause.
Under FAR 32.009-1, agencies must provide accelerated payments to small business contractors, to the fullest extent permitted by law, with a goal of paying within 15 days after receipt of a proper invoice. Primes that receive accelerated payments are expected to pay their small business subcontractors within 15 days of receiving the government's payment (clause 52.232-40). This is a goal, not an entitlement — late-payment interest still runs from the 30-day Prompt Payment due date.
The Prompt Payment clock does not start until the billing office receives a proper invoice. FAR 32.905(b) lists what it must contain:
If an invoice is missing something, the billing office must return it within 7 days of receipt with the reasons it is defective. If it returns it late, the number of days available for timely payment is reduced accordingly. Either way, a rejected invoice resets your clock — so the fastest way to get paid is to get it right the first time.
Paper invoices are largely gone. Your contract's payment clauses name the system and the routing data you must use.
DoD contracts include DFARS 252.232-7003 (electronic submission of payment requests and receiving reports) and usually 252.232-7006, which gives the Wide Area WorkFlow (WAWF) instructions: document type, and the routing DoDAACs for the pay office, issuing office, admin office, inspector, and acceptor.
Many civilian agencies use the Treasury's Invoice Processing Platform (IPP), a free, web-based system where vendors receive purchase orders, submit invoices, and track payment status. Some agencies run their own portals instead, and your contract will say which one applies.
Payment itself is made by electronic funds transfer to the bank account in your SAM.gov registration (FAR 52.232-33). An expired registration or a changed bank account that was not updated in SAM is a common, entirely avoidable cause of delayed payments. Keep your UEI and CAGE code details consistent across SAM, PIEE, and IPP.
Under FAR 52.232-7, you bill hours at the contract's fixed hourly rates plus allowable materials. Vouchers may be submitted not more than once every two weeks, though small businesses may receive more frequent payments. Be ready to substantiate hours with timesheets and to show that each person billed meets the labor category qualifications. The contracting officer may require a 5% withhold of amounts due, capped at $50,000 for the contract, released when you deliver the final release. The completion voucher is due as promptly as practicable after the work is complete and no later than 120 days after completion unless the contracting officer approves a longer period.
Under the Allowable Cost and Payment clause (FAR 52.216-7), you submit interim public vouchers (traditionally on the SF 1034 format, now electronically) for allowable costs incurred, billed at provisional indirect rates. Large businesses may bill no more than once every two weeks; small businesses may bill more often. On DoD contracts, vouchers route through WAWF, where the Defense Contract Audit Agency (DCAA) reviews them or provisionally approves them for payment and samples them afterward.
Two deadlines in that clause drive final payment:
If you miss the completion voucher deadline, the contracting officer may determine the amounts due on their own and issue a unilateral modification — which becomes a final decision under the Disputes clause. That is rarely in the contractor's favor. Getting to this stage requires an accounting system that can segregate costs by contract; see DCAA compliance and indirect rate structures.
This is one of the most-searched questions about federal billing, and the honest answer is that it depends on the contract type and its clauses:
| Situation | Deadline or practical limit |
|---|---|
| Cost-reimbursement completion voucher | 120 days after final indirect rates for all years are settled (FAR 52.216-7), unless extended in writing |
| T&M / labor-hour completion voucher | No later than 120 days after completion of the work (FAR 52.232-7), unless extended |
| Fixed-price and commercial contracts | No single FAR deadline — check your contract's invoicing instructions and agency clauses, which often set one; bill immediately after acceptance |
| Contract Disputes Act claims | A claim must be submitted within 6 years after it accrues (41 U.S.C. 7103) |
| Government file closeout targets | FFP: 6 months after physical completion; cost-type with indirect rates: 36 months; other: 20 months (FAR 4.804-1) |
Three practical risks make "later" expensive even where no hard deadline applies:
If you discover an unbilled amount on a closed contract, contact the contracting officer in writing, explain the amount, and submit the invoice through the contract's system if it is still open to you. If payment is refused, the path is a claim under the Disputes clause. The contract closeout guide covers the rest of the closeout sequence.
Small businesses financing a contract through a bank or factor often need the government to pay the lender. The Assignment of Claims Act, implemented at FAR Subpart 32.8 and clause 52.232-23, allows it only if:
Until the notice is filed and acknowledged, the government keeps paying you. A contract may also prohibit assignment, and a no-setoff commitment is available only in limited circumstances.
Keep a simple invoice log (number, date submitted, amount, status, date paid, interest paid). It makes late payments easy to spot and gives you the record you need if you have to escalate to the contracting officer or pursue a claim. For changes that affect what you can bill, see contract modifications.
Generally 30 days. Under the Prompt Payment Act and FAR 32.904, payment is due on the later of the 30th day after the billing office receives a proper invoice or the 30th day after government acceptance, with acceptance deemed to occur on the 7th day after delivery for interest purposes unless the contract says otherwise. Construction progress payments are due in 14 days.
It depends on the contract. On cost-reimbursement contracts the completion voucher is due within 120 days after final indirect rates are settled (FAR 52.216-7), and on T&M contracts within 120 days after the work is completed (FAR 52.232-7), unless the contracting officer extends it. Fixed-price contracts have no single FAR deadline, but agency clauses often set one, and once you sign a final release or the funds are de-obligated or cancelled, collecting becomes much harder. Disputed amounts must be claimed within 6 years under the Contract Disputes Act.
Yes. If a proper invoice was received, the work was accepted, and there is no dispute, the payment office must add Prompt Payment interest automatically without a request. The rate is set by Treasury every six months; it is 4.75% for July 1 through December 31, 2026. If the interest is not paid, you can demand an additional penalty in writing within 40 days after the principal is paid.
It must include your name and address, invoice date and number, contract and order number and CLIN, a description with quantity, unit price and extended price, shipping and payment terms, the payee's name and address, a contact for defective invoices, TIN and EFT information if required, and any other documentation the contract requires. Defective invoices must be returned within 7 days.
DoD contracts use Wide Area WorkFlow (WAWF) in the PIEE system, following the routing instructions in DFARS 252.232-7006. Many civilian agencies use Treasury's free Invoice Processing Platform (IPP), while some use their own portals. The invoicing instructions in your contract name the system to use.
The most common reasons are routing codes that do not match the contract's payment instructions, the wrong document type, billing against an unfunded or wrong CLIN, prices that do not match the contract, billing before acceptance, duplicate invoice numbers, and SAM registration or banking mismatches. The rejection notice usually states the reason; fix it and resubmit under a new or corrected invoice as the system requires.
Yes, through an assignment of claims under FAR Subpart 32.8 if the contract totals $1,000 or more, the assignee is a bank, trust company, or other financing institution, the assignment covers all unpaid amounts, and written notice with a true copy is filed with the contracting officer, any surety, and the disbursing officer.
Authoritative sources: FAR Subpart 32.9 — Prompt Payment, FAR 52.216-7, Treasury Prompt Payment, and IPP. This page is general information, not legal advice; your contract's payment clauses control.